By Emmanuel Njaprim
Communication Officer
The Taraba State Agro-Climatic Resilience in Semi-Arid Landscapes (ACReSAL) Project has inspected the ongoing Ndibam Gully Erosion Control Project in Takum Local Government Area, reporting 75 per cent completion.
The inspection, led by the State Project Coordinator, Dr. Yakubu Giwa Clement, was conducted to assess the progress of construction, evaluate the quality of work and identify challenges requiring urgent intervention.
During the visit, the Project Coordinator expressed concern over the refusal of some Persons Affected by the Project (PAPs), who had received compensation for their properties, to vacate the project site.
He said their continued occupation of the compensated properties was obstructing construction activities and slowing down the contractor’s progress.
Addressing the issue, Dr. Giwa appealed to the Chairman of Takum Local Government Area to intervene and ensure that the affected persons vacate the premises immediately.
“Chairman, please tell these people to vacate these premises with immediate effect. They are obstructing the construction work. You cannot collect government money to leave the site and still remain in the same place you collected compensation for,” he emphasised.
The inspection team also engaged the project consultant on technical issues relating to the gully erosion control works, offering recommendations aimed at ensuring a lasting solution to the persistent erosion challenge in the community.
Despite the challenges, the SPMU reported that construction activities were progressing satisfactorily and generally in line with the approved engineering specifications.
Earthworks, drainage structures and foundation works were observed at different stages of completion during the inspection.
According to the project update, the Ndibam community has a total of 134,576 project-affected beneficiaries, comprising 68,062 males, representing 50.6 per cent, and 66,514 females, representing 49.4 per cent.
The project has attained approximately 75 per cent completion, with the SPMU expressing optimism that it will reach 99 per cent completion within the next two months, subject to the resolution of outstanding challenges.
The Taraba ACReSAL SPMU reiterated its commitment to ensuring that the Ndibam Gully Erosion Control Project is completed in accordance with the required engineering standards to provide a sustainable solution to erosion, protect lives and properties, and improve environmental resilience in the area.